MASTER PRODUCTION
SCHEDULE
Master production schedule
is a master level or top level schedule used to set the production plan in a manufacturing
facility. It is usually a medium-term production plan indicating the start of
manufacturing in quantities and lead times for each article according to demand
and the company’s capacity. The MPS is used in particular to establish the
Material Requirements Plan.
If you recall the S&OP
process flow diagram from Collaborative SupplyChain – II and AM PPG Inc’s coffee mug demand plan example from Sales Forecasting and Demand Planning, our demand
plan, which is an output of S&OP process, depicts only aggregate demand of
coffee mug (product group) instead of individual products (small, medium and
large sizes). MPS disaggregates the S&OP demand plan data into a medium
term production plan. MPS, therefore, is a statement of production not a
statement of demand. It serves as contract between sales and production by
firming the production dates and quantities and takes into account the capacity
limitations.
In the following example, I
have developed the Master Production Schedule (MPS) taking the demand plan of
April, May and June months of year 2013 into account and assuming that our
aggregate production plan has the same figures:
Demand Plan for April, May and June, 2013:
Master production Schedule (MPS) for April, May and
June, 2013:
Since MPS is the basis for manufacturing budgets, the
financial budgets should be integrated with production planning/MPS activities.
When MPS is extended over a time horizon, it provides an effective ground for
capital budgeting. One can forecast about the day-to-day cash flow based on the
production output specified in the MPS. The MPS should be realistic and not
overstated.
MPS development takes place
in three phases:
- Development of the first version of MPS
- Rough cut capacity planning to ensure that target production quantities are achievable
- In case if capacity is overloaded and insufficient, S&OP team revises the plan to develop a more viable version of MPS
MPS focus varies for
different demand type/ production strategies.
MPS Inputs and Outputs:
Master Scheduling Grid
(MSG):
In addition to aggregating
data from the production plan, MPS also incorporates booked orders and
inventory data in the form of master scheduling grid. Master scheduling grid is
time phased and renders the information about:
- Planning Horizon
- Projected Available Balance (PAB)
- Available-to-Promise (ATP)
Below is an example of
Master Scheduling Grid (MSG) where the forecast figures have been taken from
our coffee mug MPS:
As you can see in the above
example:
- MPS-MSG takes Forecast and Customer Orders into account.
- It has a total 12 weeks of planning horizon
- It also has Demand Time Fence (DTF) and Planning Time Fence (PTF)
Now let’s see what is
planning horizon and what this time fence concept is all about.
Planning Horizon:
APICS defines planning
horizon as “A cumulative period of time for which plan has been extended
into the future”.
Planning horizon must be
long enough to equal, at a minimum, the longest cumulative or end-to-end lead
time of any item in the planning period. This includes engineering time (in
custom design environment), procurement time and production time.
Time Fence:
According to APICS definition
“A time fence marks off a zone in which otherwise available product may
not be promised-to-deliver without permission”.
There are three types of
time fences-
Demand Time Fence (DTF):
This is also known as
Minimum Zone or Frozen zone. MPS can not be changed in this period as materials
are committed to specific orders and these orders are frozen inside the fence. It
provides stable targets for manufacturing to hit. DTF is comparatively shorter
than PTF. In DTF, forecast is ignored in calculating the available. Any
modification needs endorsement of top management as shown in the below diagram:
Planning Time Fence
(PTF):
In this time period,
capacity of resources and material are not as strongly committed to orders as
in DTF. Planning fence indicates the time period in which the master production
scheduler plans for more MPS quantities. In this zone, there is a room for
negotiation in the form of management tradeoffs. PTF is also known as slushy
zone.
Liquid Zone:
Master production scheduler
can make changes outside the planning time fence. This zone is known as liquid
zone. All changes are allowed in this zone as long as they do not violate the
limits set in the production plan or by the policy in the S&OP plan.
Below diagram clearly explains
the time fence concept:
Projected Available
Balance (PAB):
PAB is a projected future
inventory balance. PAB’s drop below the safety stock level or to a negative
value alarms the MPS reevaluation. Here is how we calculate PAB:
PAB before DTF:
PAB = PAB from the last
period + MPS – Customer Orders
PAB after DTF:
PAB = PAB from the last
period + MPS – Greater of Customer Orders or Forecast
Below example is in
continuation of our MSG and shows calculation of PAB:
Available-to-promise
(ATP):
As the name suggests, ATP
is uncommitted portion of the inventory and planned production maintained in
MPS. Here is how we calculate ATP:
First period ATP = IOH*
+ MPS - Sum of customer orders before next MPS
(IOH* = Inventory on hand)
Following period ATP =
MPS - Sum of customer orders before next MPS
Since following period does
not include IOH, IOH is not taken in the calculation.
Below diagram is in
continuation of PAB diagram and shows the calculation of ATP:
I hope the above explanation is good enough to make
MPS easily understandable. I tried my best but still should you need any help,
please feel free to leave your questions in the comments.
Dear Arvin,
ReplyDeletevery nice explanation on how MPS works. I am faced to some doubts when implementing it:
1. how do you identify (how many weeks) the cumulative lead time for a Make to Stock (finished products) MPS grid ?
2. under above scenario how do yoi identify when starts and when finishes your demand time fence ?
thanks a lot
Luis